Management activities for construction of a dike
Abstract
The dike is an engineering construction and is a component part of the hydrotechnical arrangements. A case study regarding the management of the construction activities of a dike is described in this paper. Alternative mechanization options are presented, and their selection criteria were to fit into the execution period and financial efficiency. In this sense, a calculation of premeasurements, required construction machines, number of hours of their operation, specific fuel consumption, working days for each activity is presented.